I-64 / I-295 Interchange Modification Project Photos - February 2008 |
This article has 45 photos, with 19 photos by Roads to the Future, and 26 photos by VDOT.
The following 19 photos were taken on February 2, 10 and 24 by Roads to the Future. Click on the photo to get a large version of the photo. The large photos have sizes ranging from 145 to 248 kilobytes, with most of them being under 203 kilobytes. With a broadband or network Internet connection each photo will download within seconds, but with a dial-up Internet connection it will be somewhat slower.
Photos below taken on February 2, 2008 |
|
I-64 westbound (toward Charlottesville), one half mile east of the VA-288 interchange, a third lane is being constructed on the right. The third right lane to the VA-288 interchange, begins ahead, and the current construction project ends. The third right lane will extend seamlessly between the I-295 and VA-288 interchanges. Notice the overhead sign for the exit to VA-288 southbound. Asphalt base material has been placed for the new lane and shoulder. | |
I-64 westbound (toward Charlottesville), one mile east of the VA-288 interchange, a third lane is being constructed on the right. Asphalt base material has been placed for the new lane and shoulder. | |
I-64 eastbound
(toward Richmond), approaching the under construction 2-lane ramp from eastbound
I-64 to eastbound I-295 (toward Washington and Norfolk).
Approaching the VA-271 Pouncey Tract Road overpass over I-64. The original 2-lane bridge is being replaced with a 4-lane bridge that is long enough to span the widened approaches on I-64 to I-295. Looking at the under construction southbound portion of the bridge. Notice the steel girders for the new bridge, that are stationed on the other side of the concrete barricade to the right of traffic, awaiting placement on the new bridge. This and the next 2 photos are in driving sequence. |
|
I-64 eastbound
(toward Richmond), approaching the under construction 2-lane ramp from eastbound
I-64 to eastbound I-295 (toward Washington and Norfolk).
Approaching the VA-271 Pouncey Tract Road overpass over I-64. The completed new northbound portion of the bridge is temporarily carrying 2-lane 2-way traffic. |
|
I-64 eastbound,
passing the under construction 2-lane ramp from eastbound I-64 to eastbound
I-295. The flyover bridge is the higher bridge, and the original I-295 bridges
are at the lower bridge level.
Notice the Mechanically Stabilized Earth (MSE) retaining walls constructed on the earthen fill approach to the flyover bridge. The end of the retaining wall structure has the abutment (bridge terminal structure) where the bridge begins. The flyover bridge will be 1,765 feet long and 35 feet above I-64. |
|
Approaching
the under construction flyover bridge. The westbound I-295 roadway is carrying
2-way traffic; this is a temporary arrangement instituted as part of this
project. I-295 has a temporary roadway for the pre-existing interchange loop
ramp movement from eastbound I-64 (toward Richmond) to eastbound I-295 (toward
Washington and Norfolk). The inner lane of the I-295 3-lane westbound roadway
(toward Charlottesville) is being used as this temporary roadway, and there
are temporary roadway connections between the pre-existing loop ramp and this
roadway, and between this roadway and the permanent I-295 eastbound roadway.
This temporary roadway was necessary so that a segment of eastbound I-295
could be vacated of traffic so that it could be reconstructed to include the
downstream elevated approach from the flyover bridge.
This and the next photo is in driving sequence (eastbound I-64 to eastbound I-295). |
|
Crossing
the I-295 bridge over I-64, approaching the under construction flyover bridge.
The steel girders for the bridge roadway deck have been placed on most of
the spans of this bridge, and more will be placed in the near future.
Photo #7 |
|
This is
the reverse view of the previous photo, from the ramp from I-295 westbound
(toward Charlottesville) to I-64 eastbound (toward Richmond).
The inner lane of the 3-lane I-295 westbound roadway is on the other side of the concrete barricade, as is being used for the I-295 temporary roadway for the interchange ramp movement from eastbound I-64 to eastbound I-295 (toward Washington and Norfolk). The under construction eastbound flyover ramp is visible ahead, and the placement of steel girders for the bridge has been partially completed. Photo #8 |
|
Steel beam placement has been partially completed for the 2-lane flyover bridge from eastbound I-64 to eastbound I-295 (toward Washington and Norfolk). Looking across the loop ramp from westbound I-295 to eastbound I-64 (toward Richmond). | |
Steel
beam placement has been partially completed for the 2-lane flyover bridge
from eastbound I-64 to eastbound I-295 (toward Washington and Norfolk). Looking
across the loop ramp from westbound I-295 to eastbound I-64 (toward Richmond).
Notice the 'straddle bents' on the flyover bridge ... they are utilized
when a bridge crosses over a roadway at a very high skew (angle of difference
from the perpendicular), to where conventional piers would have to be placed
in the middle of the roadway, so the cross-member extends well outside of
the bridge footprint, so that the piers are outside of the roadway below. |
|
Steel beam placement has been partially completed for the 2-lane flyover bridge from eastbound I-64 to eastbound I-295 (toward Washington and Norfolk). Looking across the loop ramp from westbound I-295 to eastbound I-64 (toward Richmond). | |
Photos below taken on February 10, 2008 |
|
Crossing the I-295 bridge over I-64, approaching the under construction flyover bridge, on the temporary ramp movement from eastbound I-64 (toward Richmond) to eastbound I-295 (toward Washington and Norfolk). Similar vantage point as photo #7 on February 2nd, notice that additional steel girders have been placed since then. | |
View from the I-295 temporary roadway for the interchange ramp movement from eastbound I-64 (toward Richmond) to eastbound I-295 (toward Washington and Norfolk). Ahead is the construction of the Mechanically Stabilized Earth (MSE) retaining walls on the earthen fill approach from the flyover bridge for the new semi-directional ramp from eastbound I-64 to eastbound I-295 (toward Washington and Norfolk). This is the "landing" for the flyover ramp on I-295. The end section of the flyover bridge will connect to the elevated approach, at the near end. | |
Approaching the under construction flyover bridge, on the ramp movement from I-295 westbound (toward Charlottesville) to I-64 eastbound (toward Richmond). Similar vantage point as photo #8 on February 2nd, notice that additional steel girders have been placed since then. | |
Steel beam placement has been partially completed for the 2-lane flyover bridge from eastbound I-64 to eastbound I-295 (toward Washington and Norfolk). Looking across the loop ramp from westbound I-295 to eastbound I-64 (toward Richmond). | |
I-64 westbound (toward Charlottesville), approaching the bridges to and from I-295. The under construction flyover bridge is the higher bridge, and the original I-295 bridges are at the lower bridge level. | |
Photos below taken on February 24, 2008 |
|
Crossing
the I-295 bridge over I-64, approaching the under construction flyover bridge,
on the temporary ramp movement from eastbound I-64 (toward Richmond) to eastbound
I-295 (toward Washington and Norfolk).
The under construction eastbound flyover ramp is visible ahead, and the placement of steel girders for the bridge has been partially completed. |
|
New VA-271
Pouncey Tract Road overpass over I-64. The original 2-lane bridge is being
replaced with a 4-lane bridge that is long enough to span the widened approaches
on I-64 to I-295.
Looking at the under construction southbound portion of the bridge. The completed new northbound portion of the bridge is behind (to the right of) that span. The northbound 2-lane portion of the bridge, is temporarily carrying 2-lane 2-way traffic. |
|
New VA-271
Pouncey Tract Road overpass over I-64. The original 2-lane bridge is being
replaced with a 4-lane bridge that is long enough to span the widened approaches
on I-64 to I-295.
Looking at the under construction southbound portion of the bridge. The steel girders for the bridge roadway deck have been placed on the section that spans the I-64 eastbound (toward Richmond) roadway, and steel girder placement for the rest of the bridge will be accomplished in the next few days. The completed new northbound portion of the bridge is behind (to the right of) that span. |
The following 14 photos were taken on February 25 and 26, 2008 by the Virginia Department of Transportation, and are posted here with their permission. Roads to the Future utilized PhotoDeluxe Business Edition to sharpen and brighten and to align all of the photos. Click on the photo to get a large version of the photo. You probably will need to use Full Screen mode (the F11 key can be utilized to swap back and forth between Full Screen and Regular) to see the full size of the large photo without browser-induced image shrinkage. The large photos have sizes ranging from 154 to 367 kilobytes, with most of them being under 232 kilobytes. With a broadband or network Internet connection each photo will download within seconds, but with a dial-up Internet connection it will be somewhat slower.
These photos show the under construction 2-lane southbound portion of the new VA-271 Pouncey Tract Road overpass bridge over I-64. The completed new northbound portion of the bridge is temporarily carrying 2-lane 2-way traffic. The steel girders for the bridge roadway deck have been placed on the section that spans the I-64 eastbound (toward Richmond) roadway, and steel girder placement for the rest of the bridge over the I-64 westbound (toward Charlottesville) roadway, will be accomplished in the next few days. On the overnight depicted below, 3 steel girders were placed. These placements of steel bridge girders over a highway roadway, require the temporary closing of the roadway below, as it too dangerous for the traffic below, as there is some risk (albeit very small) that during the placement operation that a girder might get dropped. Therefore during the placement operation, the westbound roadway of I-64 was closed to public traffic between US-250 Exit 178 and VA-288 Exit 175, with the traffic detoured via US-250 and VA-288. That segment of US-250 is a 6-lane arterial, and that segment of VA-288 is a 6-lane freeway. Don't have the exact times, but given how much traffic uses I-64, it would be at the lowest traffic period possible, on a weekday, and typically closing at 8:00 pm and reopening at 6:00 am the next morning.
The following 12 aerial photos were taken on February 11, 2008 by the Virginia Department of Transportation, and are posted here with their permission. Roads to the Future utilized PhotoDeluxe Business Edition to sharpen and brighten and to align all of the photos. Click on the photo to get a large version of the photo. You probably will need to use Full Screen mode (the F11 key can be utilized to swap back and forth between Full Screen and Regular) to see the full size of the large photo without browser-induced image shrinkage. The large photos have sizes ranging from 339 to 463 kilobytes, with most of them being under 436 kilobytes. The photos marked "LARGE PHOTO" are much larger, with a very detailed zoom-in of the previous photo, and they have the file size listed next to the photo. With a broadband or network Internet connection each photo will download within seconds, but with a dial-up Internet connection it will be somewhat slower.
Lead article - I-64/I-295 Interchange Modification Project
Copyright © 2009 by Scott Kozel. All rights reserved. Reproduction, reuse, or distribution without permission is prohibited.
By Scott M. Kozel, Roads to the Future
(Created 2-4-2009,updated 2-13-2009)