| SIIP Project Phase 6/7 - Dashboard Snapshots | 
Phase 6 and Phase 7 mainly focused on the remainder of the I-95/I-395/I-495 interchange, mainly the elevated ramps, but also included the remainder of the northbound I-95 roadway south of I-495. Phases 6 and 7 were constructed in one contract, was advertised for bids by VDOT on June 24, 2003, the bids were opened on September 3, 2003, the Commonwealth Transportation Board awarded the $99.8 million contract on September 17, 2003, to Archer Western Contractors Ltd., and contract completion occurred on July 17, 2007.
  The
  VDOT Dashboard has the 
	details for this project, here is a copy from March 31, 2007 below, from the
  I95/I395/I495 Interchange 
  (SIIP 
  Phase 6/7) 
  project.
	UPC - 14680 
	Contract ID - A00014680C05 
	State 
	Project # - 0095029F20 
	Description - I95/I395/I495 INTERCHANGE
	Route -  95 
	Construction Company - ARCHER WESTERN CONTRACTORS, LTD. 
	Contract
	Award Amount - $99,829,000 
	Inspector's Estimated Amount to Complete - $105,895,000
	Cost of Work To Date - $94,010,006
	Current Contract Amount - $103,486,107
	6.0% OVER ORIGINAL CONTRACT AWARD AMOUNT 
	Contractor's Notice to Proceed - October 17, 2003 
	Original Specified Completion Date - July 18, 2007 
	Current Specified Completion Date - July 18, 2007 
	Estimated Completion Date - July 18, 2007 
	% Critical Work Completed - 91% 
	% Critical Work Planned -  93% 
	Days Charged To Date -  1261 
	Current Number of Days - 1370
  TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL 
  COMPLETION DATE
  The VDOT Dashboard has the 
	details for this project, here is a copy from December 4, 2006 below, from the I95/I395/I495 Interchange 
  (SIIP 
  Phase 6/7) 
  project.
	UPC - 14680 
	Contract ID - A00014680C05 
	State 
	Project # - 0095029F20 
	Description - I95/I395/I495 INTERCHANGE
	Route -  95 
	Construction Company - ARCHER WESTERN CONTRACTORS, LTD. 
	Contract
	Award Amount - $99,829,000 
	Inspector's Estimated Amount to Complete - $105,895,000
	Cost of Work To Date - $85,214,972
	Current Contract Amount - $103,209,089
	6.0% OVER ORIGINAL CONTRACT AWARD AMOUNT 
	Contractor's Notice to Proceed - October 17, 2003 
	Original Specified Completion Date - July 18, 2007 
	Current Specified Completion Date - July 18, 2007 
	Estimated Completion Date - July 18, 2007 
	% Critical Work Completed - 81.5% 
	% Critical Work Planned - 86.9% 
	Days Charged To Date -  1190 
	Current Number of Days - 1370
  TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL 
  COMPLETION DATE
  The VDOT Dashboard has the 
	details for this project, here is a copy from August 26, 2006 below, from the I95/I395/I495 Interchange 
  (SIIP 
  Phase 6/7) 
  project.
	UPC - 14680 
	Contract ID - A00014680C05 
	State 
	Project # - 0095029F20 
	Description - I95/I395/I495 INTERCHANGE
	Route -  95 
	Construction Company - ARCHER WESTERN CONTRACTORS, LTD. 
	Contract
	Award Amount - $99,829,000 
	Inspector's Estimated Amount to Complete - $106,500,000
	Cost of Work To Date - $75,916,167
	Current Contract Amount - $103,198,218
	6.6% OVER ORIGINAL CONTRACT AWARD AMOUNT 
	Contractor's Notice to Proceed - October 17, 2003 
	Original Specified Completion Date - July 18, 2007 
	Current Specified Completion Date - July 18, 2007 
	Estimated Completion Date - July 18, 2007 
	% Critical Work Completed - 73.3% 
	% Critical Work Planned - 82.0% 
	Days Charged To Date -  990 
	Current Number of Days - 1369
  TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL 
  COMPLETION DATE
The VDOT Dashboard has the 
	details for this project, here is a copy from April 20, 2006 below, from the I95/I395/I495 Interchange 
  (SIIP 
  Phase 6/7) 
  project.
	UPC - 14680 
	Contract ID - A00014680C05 
	State 
	Project # - 0095029F20 
	Description - I95/I395/I495 INTERCHANGE
	Route -  95 
	Construction Company - ARCHER WESTERN CONTRACTORS, LTD. 
	Contract
	Award Amount - $99,829,000 
	Inspector's Estimated Amount to Complete - $108,000,000
	Cost of Work To Date - $66,524,896
	Current Contract Amount - $103,136,388 
	8.1% OVER ORIGINAL CONTRACT AWARD AMOUNT 
	Start Date - October 17, 2003 
	Original Specified Completion Date - July 18, 2007 
	Current Specified Completion Date - July 18, 2007 
	Estimated Completion Date - July 18, 2007 
	% Critical Work Completed - 64.1% 
	% Critical Work Planned - 80.0% 
	Days Charged To Date - 899 
	Current Number of Days - 1369 
	15% BEHIND SCHEDULE 
The VDOT Dashboard has the 
	details for this project, here is a copy from January 21, 2006 below, from the I95/I395/I495 Interchange 
  project.
	UPC - 14680 
	Contract ID - A00014680C05 
	State 
	Project # - 0095029F20 
	Description - I95/I395/I495 INTERCHANGE
	Route -  95 
	Construction Company - ARCHER WESTERN CONTRACTORS, LTD. 
	Contract
	Award Amount - $99,829,000 
	Inspector's Estimated Amount to Complete - $99,829,000
	Cost of Work To Date - $57,590,022
	Current Contract Amount - $103,129,388 
	3.3% OVER ORIGINAL CONTRACT AWARD AMOUNT 
	Start Date - October 17, 2003 
	Original Specified Completion Date - July 18, 2007 
	Current Specified Completion Date - July 18, 2007 
	Estimated Completion Date - July 18, 2007 
	% Critical Work Completed - 55.3% 
	% Critical Work Planned - 74.0% 
	Days Charged To Date - 809 
	Current Number of Days - 1369 
	18% BEHIND SCHEDULE 
The VDOT Dashboard has the 
	details for this project, here is a copy from October 30, 2005 below, from the I95/I395/I495 Interchange 
  project.
	UPC - 14680 
	Contract ID - A00014680C05 
	State 
	Project # - 0095029F20 
	Description - I95/I395/I495 INTERCHANGE
	Route -  95 
	Construction Company - ARCHER WESTERN CONTRACTORS, LTD. 
	Contract
	Award Amount - $99,829,000 
	Inspector's Estimated Amount to Complete - $99,829,000
	Cost of Work To Date - $49,073,247 
	Current Contract Amount - $103,118,909 
	3.2% OVER ORIGINAL CONTRACT AWARD AMOUNT 
	Start Date - October 17, 2003 
	Original Specified Completion Date - July 18, 2007 
	Current Specified Completion Date - July 18, 2007 
	Estimated Completion Date - July 18, 2007 
	% Critical Work Completed - 47.0% 
	% Critical Work Planned - 65.0 
	Days Charged To Date - 717 
	Current Number of Days - 1369 
	18% BEHIND SCHEDULE 
The VDOT Dashboard has the 
	details for this project, here is a copy from July 26, 2005 below, from the I95/I395/I495 Interchange 
  project.
	UPC - 14680 
	Contract ID - A00014680C05 
	State 
	Project # - 0095029F20 
	Description - I95/I395/I495 INTERCHANGE
	Route -  95 
	Construction Company - ARCHER WESTERN CONTRACTORS, LTD. 
	Contract
	Award Amount - $99,829,000 
	Inspector's Estimated Amount to Complete - $103,026,894 
	Cost of Work To Date - $38,904,365 
	Current Contract Amount - $103,026,894 
	3.2% OVER ORIGINAL CONTRACT AWARD AMOUNT 
	Start Date - October 17, 2003 
	Original Specified Completion Date - July 18, 2007 
	Current Specified Completion Date - July 18, 2007 
	Estimated Completion Date - July 18, 2007 
	% Critical Work Completed - 36.8% 
	% Critical Work Planned - 48% 
	Days Charged To Date - 625 
	Current Number of Days - 1369 
	11% BEHIND SCHEDULE 
Copyright © 2006 by Scott Kozel. All rights reserved. Reproduction, reuse, or distribution without permission is prohibited.
By Scott M. Kozel,
Roads to the Future(Created 12-4-2006, updated 9-16-2007)