SIIP Project Phase 6/7 - Dashboard Snapshots

Phase 6 and Phase 7 mainly focused on the remainder of the I-95/I-395/I-495 interchange, mainly the elevated ramps, but also included the remainder of the northbound I-95 roadway south of I-495. Phases 6 and 7 were constructed in one contract, was advertised for bids by VDOT on June 24, 2003, the bids were opened on September 3, 2003, the Commonwealth Transportation Board awarded the $99.8 million contract on September 17, 2003, to Archer Western Contractors Ltd., and contract completion occurred on July 17, 2007.

The VDOT Dashboard has the details for this project, here is a copy from March 31, 2007 below, from the I95/I395/I495 Interchange (SIIP Phase 6/7) project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $105,895,000
Cost of Work To Date - $94,010,006
Current Contract Amount - $103,486,107
6.0% OVER ORIGINAL CONTRACT AWARD AMOUNT
Contractor's Notice to Proceed - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 91%
% Critical Work Planned - 93%
Days Charged To Date - 1261
Current Number of Days - 1370
TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL COMPLETION DATE

The VDOT Dashboard has the details for this project, here is a copy from December 4, 2006 below, from the I95/I395/I495 Interchange (SIIP Phase 6/7) project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $105,895,000
Cost of Work To Date - $85,214,972
Current Contract Amount - $103,209,089
6.0% OVER ORIGINAL CONTRACT AWARD AMOUNT
Contractor's Notice to Proceed - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 81.5%
% Critical Work Planned - 86.9%
Days Charged To Date - 1190
Current Number of Days - 1370
TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL COMPLETION DATE

The VDOT Dashboard has the details for this project, here is a copy from August 26, 2006 below, from the I95/I395/I495 Interchange (SIIP Phase 6/7) project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $106,500,000
Cost of Work To Date - $75,916,167
Current Contract Amount - $103,198,218
6.6% OVER ORIGINAL CONTRACT AWARD AMOUNT
Contractor's Notice to Proceed - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 73.3%
% Critical Work Planned - 82.0%
Days Charged To Date - 990
Current Number of Days - 1369
TODAY <= PROJECTED COMPLETION DATE AND PROJECTED COMPLETION DATE <= ORIGINAL COMPLETION DATE

The VDOT Dashboard has the details for this project, here is a copy from April 20, 2006 below, from the I95/I395/I495 Interchange (SIIP Phase 6/7) project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $108,000,000
Cost of Work To Date - $66,524,896
Current Contract Amount - $103,136,388
8.1% OVER ORIGINAL CONTRACT AWARD AMOUNT
Start Date - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 64.1%
% Critical Work Planned - 80.0%
Days Charged To Date - 899
Current Number of Days - 1369
15% BEHIND SCHEDULE

The VDOT Dashboard has the details for this project, here is a copy from January 21, 2006 below, from the I95/I395/I495 Interchange project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $99,829,000
Cost of Work To Date - $57,590,022
Current Contract Amount - $103,129,388
3.3% OVER ORIGINAL CONTRACT AWARD AMOUNT
Start Date - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 55.3%
% Critical Work Planned - 74.0%
Days Charged To Date - 809
Current Number of Days - 1369
18% BEHIND SCHEDULE

The VDOT Dashboard has the details for this project, here is a copy from October 30, 2005 below, from the I95/I395/I495 Interchange project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $99,829,000
Cost of Work To Date - $49,073,247 
Current Contract Amount - $103,118,909
3.2% OVER ORIGINAL CONTRACT AWARD AMOUNT
Start Date - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 47.0%
% Critical Work Planned - 65.0
Days Charged To Date - 717
Current Number of Days - 1369
18% BEHIND SCHEDULE

The VDOT Dashboard has the details for this project, here is a copy from July 26, 2005 below, from the I95/I395/I495 Interchange project.
UPC - 14680
Contract ID - A00014680C05
State Project # - 0095029F20
Description - I95/I395/I495 INTERCHANGE
Route - 95
Construction Company - ARCHER WESTERN CONTRACTORS, LTD.
Contract Award Amount - $99,829,000
Inspector's Estimated Amount to Complete - $103,026,894
Cost of Work To Date - $38,904,365
Current Contract Amount - $103,026,894
3.2% OVER ORIGINAL CONTRACT AWARD AMOUNT
Start Date - October 17, 2003
Original Specified Completion Date - July 18, 2007
Current Specified Completion Date - July 18, 2007
Estimated Completion Date - July 18, 2007
% Critical Work Completed - 36.8%
% Critical Work Planned - 48%
Days Charged To Date - 625
Current Number of Days - 1369
11% BEHIND SCHEDULE

Copyright © 2006 by Scott Kozel. All rights reserved. Reproduction, reuse, or distribution without permission is prohibited.

Back to top

By Scott M. Kozel, Roads to the Future

(Created 12-4-2006, updated 9-16-2007)